Zaporizhzhia nuclear plant is receiving off-site power again after the Ferosplavna-1 line was switched on, Energoatom says
Reported1 origin: the claimant's own report, which does not count as evidence.
Energoatom said the 330 kV Ferosplavna-1 line was switched on at 17:41 Kyiv time on 8 November and that the Zaporizhzhia plant again receives off-site power from Ukraine's grid, Ukrinform reported. The plant had lost that line early the same morning.
- When
- 8 November 2026
- Where
- Zaporizhzhia nuclear power plant, Ukraine
- What
- other
- Attribution
- Not attributed. The restoration is reported by Energoatom alone; no one is named as having carried out an attack in this report.
- In the record
- Published 2026-11-09 01:34 UTC
Sources
History
- First recorded 9 Nov, 01:34 UTC, as reported (one origin only).
Cite or reuse
The War Record, "Zaporizhzhia nuclear plant is receiving off-site power again after the Ferosplavna-1 line was switched on, Energoatom says", record ev-20261109-tn27, version 1, https://thewarrecord.com/events/ev-20261109-tn27/